Plumber on a front entrance path with new trench grates laid out and an excavator behind

Case study · Stormwater drainage

Stormwater Drainage and Pipe Repairs at an Early Education Centre in Jannali

An early education centre in Jannali needed new drainage at its front entrance and had stormwater pipes crushed by tree roots out the back. We built a new concrete path with trench grates, dug out and replaced the damaged pipes, ran a steel pipe under a large tree root to a new 600mm pit, and connected ten downpipes to the stormwater, five of them over new pits.

Property

Early education centre, front entrance and rear play areas

Location

Jannali, Sutherland Shire

Scope

Trench grates and a new concrete path, CCTV drain inspection, high pressure jetting, tree root removal, stormwater pipe repairs, new pits, downpipe connections and a new concrete step

Time on site

March to September 2026, in stages

Dug up stormwater pipe with tree roots inside

Stormwater Drainage and Pipe Repairs at an Early Education Centre in Jannali

The work started at the front entrance path. When we flow tested the rest of the site, the stormwater drains were blocked in separate areas.

Craig measured up the front entrance path in March, and the quote for new trench grates and a new concrete path was approved that month. That work was finished in June.

On 22 August Craig, Kye and Riley flow tested every stormwater drain on the site and found blockages in separate areas. They high pressure jetted the drains and pits, then put the camera through. The CCTV inspection showed tree roots getting into the pipes and crushing them in several places. On one line beside the building, the camera showed the pipe was crushed and full of roots, so it had to be dug up.

Why Jetting Alone Was Not Enough

Jetting clears a blockage, but it cannot fix a pipe that roots have crushed. Once the camera showed the damage, the lasting fix was to dig up those sections and replace them.

4

Crew on the job: Craig, Kye, Riley and Ethan

10

Downpipes connected to the stormwater

600mm

New concrete stormwater pit, formed and poured on site

150mm

Main stormwater line found and reconnected under a large tree root

Photos From the Jannali Stormwater Job

Photos of the new entrance path, the crew at work, the root damage and the new pits. Tap any photo to see it larger.

The Front Entrance Path, Before and After

The old paved path at the front entrance was cut out and replaced with a new concrete path, with galvanised trench grates across it and along its side to catch the water.

Before

Old paved front entrance path before the new drainage

Before: the old paved path at the front entrance.

After

New concrete entrance path with galvanised trench grates

After: the new concrete path with trench grates across it and along its side.

How We Built and Repaired the Stormwater System

The work ran in stages from March to September 2026, including some Saturday work.

01

Trench Grates and a New Entrance Path

Craig measured up the front entrance path and the quote was approved in March. The crew cut out the old paving, set galvanised trench grates in formwork with reinforcing steel, poured the new concrete path on 6 June, then stripped the formwork and laid the edging bricks.

02

New Downpipes and Pits in the Play Area

From June to early September Riley connected 100mm steel downpipes to the drainage under the concrete. On Saturdays Craig, Kye and Riley cut back the synthetic grass, found the drains and installed new pits and grates under five of the downpipes, then fitted new painted downpipes that run over them.

03

Camera Inspection and Root Damage Dug Out

After the flow test, jetting and camera inspection, Kye and Riley dug out the damaged lines, removed the tree roots and replaced the crushed 100mm sections, including 2 metres in one run. Where roots and an agricultural drain were blocking the main line, they found the 150mm main, cut out the junction and replaced it. Two new pits went in at the front and side of the building.

04

A Steel Pipe Under a Large Tree Root and a New Step

Beside a large tree, the crew broke out the old concrete pit and dug around the roots to find the 150mm main. They fitted a 150mm PVC to steel adaptor, ran a steel pipe under the root to a new 600mm pit, encased the joint in 32MPa concrete and poured the pit on site. At the side gate they broke out the old step, set the levels with a laser and poured a new reinforced slab with a broom finish.

Stormwater Drainage Result in Jannali

The centre has a new entrance path that drains through trench grates, and its stormwater now runs through repaired pipes and new pits. The large tree stays in place.

  • Front entrance: The path is now new concrete with galvanised trench grates.
  • Downpipes: Ten downpipes are connected to the stormwater, and five of them run over new pits and grates.
  • Crushed pipes: The damaged sections were dug out, the roots removed and the 100mm pipe replaced.
  • The 150mm main: The junction was replaced where roots and an agricultural drain were blocking it.
  • Under the tree: A steel pipe now runs under a large tree root to a new 600mm concrete pit.
  • Side gate: A new concrete step was poured with a broom finish.

The first stormwater quote for the centre was just over $24,000. Every site is quoted after we have had a look.

Tree Roots in Your Stormwater Pipes?

Roots find their way into small cracks and joints, then grow until they block or crush the pipe. A camera inspection shows where the damage is, so only the broken sections need digging up.

Licensed Blocked Drain Plumbers Since 2000

The Blocked Drain Guys operate under Plumb-Quick Pty Ltd, with NSW Fair Trading Contractor Licence 93566C and Qualified Supervisors Licence 67936C. We have been doing this for over 26 years. ABN 86 081 868 984.

Check our licence with NSW Fair Trading
  • Contractor
    Licence
    93566C
  • Qualified
    Supervisors Licence
    67936C
  • Clearing
    drains since
    2000

Get a free quote

Tell us what's blocked and we'll call you back with honest advice and a fixed upfront price.

Quote Request
Prefer to talk?Call 0418 408 333

Contact details

Office hoursMon – Sat 8.00 – 18.00. Sunday CLOSED
Call nowGet a free quote