Case study · Commercial plumbing

New Bubbler Station Plumbing at Engadine Leisure Centre

At the Engadine Leisure Centre on Anzac Avenue we disconnected an old bubbler and built the plumbing for a new bubbler station. We excavated, ran new copper water lines and a drainage connection, and set the base in a new concrete slab with wheelchair access.

Property

Leisure centre and pool grounds

Location

Anzac Avenue, Engadine

Scope

Old bubbler disconnection, excavation, copper water lines, drainage connection, bubbler base, formwork, steel and concrete slab

Time on site

March and April 2026

Site photo marked up with the new bubbler station layout

New Bubbler Station Plumbing at Engadine Leisure Centre

An old blue bubbler near the pool was being replaced by a new bubbler station behind a bench seat, with wheelchair access and a slab level with the path.

The site plan was marked up on 9 March 2026, and the quote was approved the same day. The new station needed a water supply, a drain and a concrete slab finished at the same level as the existing path.

All of it sat in the grounds of a public pool, so the work areas were fenced off.

Bubbler Plumbing Set Out to the Plan

The bubbler base was installed to the set-out distances on the plan, and the finished concrete level matches the existing path.

Same day

Quote approved the day of the site visit

About 2m x 300mm

Existing concrete saw cut and jackhammered

1560 x 2000 x 250mm

Concrete slab

4

Crew on the job: Craig, Ethan, Riley and Will

Photos From the Engadine Bubbler Station Plumbing

Photos from the plan, the fencing, the excavation, the pipework and the formwork. Tap any photo to see it larger.

Old Style Bubblers Replaced With Modern Bubbler Stations

An old style bubbler at the leisure centre. The modern bubbler station near the amenities sits in a new concrete slab with wheelchair access, its own water supply and a drain. Now people can fill up their water bottles too.

Before

Old style blue bubbler at the leisure centre

Before: an old style bubbler.

After

Modern bubbler station on a new concrete slab beside the amenities at the leisure centre

After: a modern bubbler station on its new concrete slab.

How We Built the Plumbing for the New Bubbler Station

Site work from 9 March to 23 April 2026.

01

Old Bubbler Disconnection and Fencing

We fenced the old blue bubbler, disconnected it and fitted a valve on its water supply, then fenced the new station's spot behind the bench seat.

02

Excavation and Concrete Cutting

We removed the bench seat, cut out the kerb and brought in an excavator. We dug the trench to the bubbler base, saw cut and jackhammered about 2m x 300mm of existing concrete, and dug a deeper section for the base footing.

03

Copper Water Line and Drainage Connection

We connected a 20mm copper line to the existing ball valve and ran a 15mm copper line to the station with an isolation ball valve. For the drain, we core drilled a 100mm hole into the earthenware pipe, fitted a 100mm 90° bend and secured it with FlashCrete, then ran the drainage line to the bubbler.

04

Bubbler Base, Formwork, Steel and Concrete

We installed the bubbler base to the plan, built timber boxing around the slab, drilled pins into the existing slab and laid steel mesh. After the concrete, the formwork came off and the area was cleaned up.

Bubbler Station Plumbing Result in Engadine

The new station has its own water supply with an isolation valve, a drain into the existing line and a concrete slab with wheelchair access. The job was completed on 28 April 2026.

  • Quote approved the day of the site visit
  • Bubbler base set out to the plan
  • Work areas fenced off
  • Materials: 15mm copper pipe, a 20mm x 15mm copper reducer, three 15mm fittings, foam lagging, steel mesh and FlashCrete

The plumbing and concrete for the new station came in at just over $17,000. That covered the excavation, the copper lines, the drainage connection, the bubbler base and the slab. Every site is quoted after we have had a look.

Adding a Bubbler or Water Station? Plan the Drain and Supply First

A new bubbler needs a water supply, a drain and a level base. Finding the existing valve and drain line first keeps the dig small.

Licensed Blocked Drain Plumbers Since 2000

The Blocked Drain Guys operate under Plumb-Quick Pty Ltd, with NSW Fair Trading Contractor Licence 93566C and Qualified Supervisors Licence 67936C. We have been doing this for over 26 years. ABN 86 081 868 984.

Check our licence with NSW Fair Trading
  • Contractor
    Licence
    93566C
  • Qualified
    Supervisors Licence
    67936C
  • Clearing
    drains since
    2000

Get a free quote

Tell us what's blocked and we'll call you back with honest advice and a fixed upfront price.

Quote Request
Prefer to talk?Call 0418 408 333

Contact details

Office hoursMon – Sat 8.00 – 18.00. Sunday CLOSED
Call nowGet a free quote