Stormwater Drainage and Pipe Repairs at an Early Education Centre in Jannali
The work started at the front entrance path. When we flow tested the rest of the site, the stormwater drains were blocked in separate areas.
Craig measured up the front entrance path in March, and the quote for new trench grates and a new concrete path was approved that month. That work was finished in June.
On 22 August Craig, Kye and Riley flow tested every stormwater drain on the site and found blockages in separate areas. They high pressure jetted the drains and pits, then put the camera through. The CCTV inspection showed tree roots getting into the pipes and crushing them in several places. On one line beside the building, the camera showed the pipe was crushed and full of roots, so it had to be dug up.
Why Jetting Alone Was Not Enough
Jetting clears a blockage, but it cannot fix a pipe that roots have crushed. Once the camera showed the damage, the lasting fix was to dig up those sections and replace them.